The works consisted of:-
The installation of large items of kit onto steelwork or prepared plinths, sludge dryers, acid/alkaline scrubbers, various pump stations, IP and HP steam heater, flash vessel, various conveyors, ID fan, are examples of the kit that was installed.
The erection of the electrostatic precipitator (ESP). The kit was delivered to site piecemeal. The hopper and sidewalls were welded together on site and lifted into position building up from the bottom to a height of 30 metres from floor level.
The internals, rappers and roof sections were then installed.
The access and support steelwork and thermal insulation were also included in our scope of works.
Sections of stainless steel and mid steel ducting up to 1600mm diameter were installed, welded on site and expansion joints fitted
Alpha Plus appointed persons created lift plans and supervised all cranage required to install the above kit. 500,250 and 100 tonne cranes were mostly used.
ESP Assembled and being installed, including internal electrode system.
The supply and manufacture of various pipelines were in Alpha Plus scope and included:
- De-min water, centrate in stainless steel.
- Fuel oil, natural gas, boiler feed water – mild steel.
- Compressed /instrument air – galvanised mild steel
- HP steam and Condensate – 1.6% crome molybdenum.
- Acid / alkaline – GRP .
New incineration plant under construction.
In addition to the main contract we were also awarded a contract to supply manufacture and install the cross site pipe work feeding the new incinerator.
Cooling water system – Mild steel
Site waste water system – Thin wall stainless steel Caustic- Dual contained PVC.
Process and potable water – mild steel ABS